SavCon Recently Completes the Construction at 801 Axxin Avenue.
May 10, 2022
Completed Traffic Court building at 801 Axxin Ave by SavCon. Photo by Matthew Windmiller, Senior Project Manager at SavCon, LLC. April 29, 2022.
Work is complete at the 30,000-square-foot traffic court building in Garden City, New York by General Contractor, SavCon, LLC.
The $3.7 million dollar project was performed for the county on behalf of the building’s landlord. The existing department of motor vehicles build-out was selectively demolished ahead of the reconstruction effort.
The build-out, which began construction in October 2021, of the local municipality’s traffic, parking and violations agency included case hearing rooms, offices, new staff and patron restrooms in addition to conference and break rooms for county employees. The entrance vestibule leads visitors to a brand-new 3,000-square foot waiting room. The aggressive schedule that SavCon put into place allowed for move-in activities just 18 weeks after demolition commenced.
SavCon’s Project Manager on the job, Matthew Windmiller, says, “Updates to the space were beyond cosmetic as the agency’s building now boasts updated fire alarm, mechanical and electrical systems.” SavCon team on the job include: Superintendent: Brian Heinlein, Superintendent, Matthew Windmiller, Project Manager, and Alejandro Diaz, Assistant Project Manager.
Completed court room by SavCon. Photo by Matthew Windmiller, Senior Project Manager at SavCon, LLC. April 29, 2022.